The shell of the swell box awaiting its roof, front doors and final painting before the pipes are installed
The hoist arrived from HSS Tool Hire at 8.15am yesterday (18th December) and Emily and I applied the last coats of paint to the rear sections of the Swellbox in readiness for its rebuilding. The team from Thompsons arrived at 11am with the new swell division (apart from its new Bassoon pipes) and other parts that had been built in the workshop.
By 1pm the pedal bass and principal windchests were fixed in place on the back wall and the bottom pipes of the Pedal 16′ Subbass were fitted. Later in the day the Swellbox side, front and rear sections were lifted into place and built on to its frame, the Swell windchest was hoisted into place inside it, and the Swell pipes were lifted onto the gallery.
Once the swellbox roof is fitted the whole swellbox will receive its final coats of paint, and be ready for its pipes to be installed and the refurbished swell doors to be fitted on the front.